THE NEW VALUE FRONTIER
  1. Home
  2. News
  3. 2018
  4. KYOCERA TCL Solar Completes 29.2MW Solar Power Plant on Repurposed Land in Japan

News

KYOCERA TCL Solar Completes 29.2MW Solar Power Plant on Repurposed Land in Japan

Company’s largest solar power plant repurposes abandoned golf course to provide equivalent power for approximately 12,000 average households

  • Solar Electric Systems

Kyoto/London − Kyocera and Tokyo Century Corporation (herein “Tokyo Century”) announced that Kyocera TCL Solar LLC (herein “Kyocera TCL Solar”) has completed construction of a 29.2 megawatt (MW) utility-scale solar power plant in Yonago City, Tottori Prefecture, Japan. The solar modules were installed on 1.2km2 of land originally designated for a golf course and other purposes but subsequently abandoned. A ceremony was held on April 27 to commemorate completion of Kyocera TCL Solar’s largest solar power plant.

kyocera_tcl_solar_completes_29_2mw_solar_power_plant_on_repurposed_land_in_japan_.-cps-000100-image.cpsimage.jpg
29.2 MW plant in Yonago City (left) and commemoration ceremony (right)

108,504 Kyocera solar modules will generate an estimated 36,080 megawatt hours (MWh) per year — enough electricity to power approximately 12,000 typical households*1. All electricity generated at the plant will be sold to the local utility (The Chugoku Electric Power Co., Inc.). Since Tottori Prefecture has a Japan Sea coastal climate with heavy snow and short hours of sunlight during the winter months, it is not always considered to be a suitable area for constructing a solar power plant. However, the company overcame such difficulties by optimizing installation methods to allow for weather conditions of the area and ensure sufficient power generation capacity.

Kyocera TCL Solar has constructed 63 solar power plants across Japan including this 29.2 MW plant with approximately 215 MW*2 of total output since the company was established in August 2012. Kyocera TCL Solar, Kyocera and Tokyo Century remain committed to promoting renewable energy as well as contributing to environmental protection and the creation of a sustainable society through their solar energy business.

Project Overview
Operation Kyocera TCL Solar LLC
Location Yonago City, Tottori Prefecture, Japan
Area Approx. 1.2km²
Output Approx. 29.2 MW
Expected annual power generation Approx. 36,080 MWh
(enough electricity to power approximately 12,000 typical households)
Solar modules 270-watt Kyocera modules (108,504 modules in total)
Electric power sales destination The Chugoku Electric Power Co., Inc.
Start of operation April 2, 2018 (Start of construction: September 2015)
Design & construction TESS Engineering Co., Ltd.
Maintenance Kyocera Solar Corporation

Company Overview
Company name
Kyocera TCL Solar LLC
Location
Chiyoda-ku, Tokyo, Japan
Shareholders
Tokyo Century Corporation (81 %)
Kyocera Corporation (19 %)
Established
August 2012

*1 Based on average annual use of 2,973.6 kWh per household. Source: Japan Atomic Energy Relations Organization (Graphical Flip-chart of Nuclear & Energy Related Topics)
*2 Total output of the plants in operation as of April 26, 2018

For more information about Kyocera: www.kyocera.eu

Press Material